Here’s what happened in May, 2020:
May 4:
- Grading for our driveway was completed and rock was spread for our construction entrance today. Our contractor also installed the silt fence.
May 6-8:
- County inspector rejected the silt fence installation and our contractor went out and re-installed it.
- County inspector approved the construction entrance and silt fence installation and left us with our grading permit to be displayed on-site.
- Next up – zoning – which is being held up by the floodplain dept (since the majority of our property is in floodplain, this has been a huge headache for us.)
- Floodplain dept apparently sent an email in February but never followed up when they didn’t receive a response. womp womp … really?! All they need is our proposed driveway and house site to be drawn on the latest version of the floodplain map. Our contractor is working this up right away but of course, it’s Friday at COB when we find this out so we won’t hear anything new from the county til Monday.
May 12-15:
- Building permit received.
- Excavation is scheduled for Monday, 5/18!

May 18-19:
- Excavation completed!

May 20-21:
- Footers and basement walls poured


May 28:
- Waterproofing done. Next week: basement plumbing and slab!

That’s it for the month of May but it sure was the most progress we have seen during our build thus far. I can’t wait to see what June has in store for us! Be sure to follow along on IG @HouseManorVA